Second Creek Recreation Center

Overview
The new recreation center is one of five projects in Commerce City’s voter-approved capital improvement program. Located at E. 112th Avenue and Potomac Street, the project includes an indoor pool, gymnasium with walking/jogging track, weights/fitness area, gymnastics room, dance/ aerobics studio and site infrastructure. In addition to the approximately 108,000 square foot building, the project will construct infrastructure on E. 112th Avenue and Potomac Street to access the new facility.

Schedule
Construction began in October 2016 and is scheduled to complete in spring 2018 (weather dependent). Typical project hours are 7 a.m. to 5 p.m. Night hours may be used to optimize road work during low-travel times.

Traffic Impacts
Crews will shift traffic to the west side of Highway 2 at E. 112th Avenue and Potomac Street for the remainder of the project. A full weekend closure of Highway 2 near Potomac Street will support demolition for the widening of the bridge over O’Brien Canal and the setting of new girders. Overnight closures are expected for the bridge removal. The closures of E. 112th Avenue and Potomac Street will remain throughout the project. Use caution and expect periodic delays, lane shifts and closures.

What’s Ahead - April and May 2017
Upcoming work includes setting structural steel and block walls in the pool area, installing the storm sewer and pouring concrete slabs. Crews will begin constructing curbs and gutters, and installing electrical in the parking areas. Crews are completing site-wide rough grading, starting fine grading for curb and gutter installation, and continuing bridge and road widening work.

Contact Information
303-C3-WORKS (303-239-6757) or visit www.c3gov.com/QCL to learn more and stay informed.